Project overview:
As part of ongoing cooperation to develop infrastructure and enhance the capital’s urban landscape, a consortium of companies — Anwar Tareeq Al-Mawasem and Abwab Al-Ola — carried out an integrated project to rehabilitate and develop 14 Ramadan Street (sewerage and development). The project was executed for the Mayoralty of Baghdad – Al-Mansour Municipality Directorate, within the “A More Beautiful Baghdad” campaign (Phase Two) to improve road efficiency and modernize vital drainage networks.


Project details:

🔹 Project name: Rehabilitation and development works of 14 Ramadan Street (infrastructure) / Phase Two.
🔹 Beneficiary: Mayoralty of Baghdad – Al-Mansour Municipality Directorate.
🔹 Executed by: Consortium of Anwar Tareeq Al-Mawasem and Abwab Al-Ola for Contracting and General Trade.
🔹 Contract value: IQD 16,292,215,000 (sixteen billion, two hundred ninety-two million, two hundred fifteen thousand Iraqi dinars).
🔹 Duration: 300 calendar days.
🔹 Start date: 10/08/2025.
🔹 Location: Baghdad – Al-Karkh (Al-Mansour area).

Project status:

In progress.